A fifth of the clock

In 2016 the drilling contractor I worked for knew how many days a well had taken. What the days were made of was harder to say. The record was the daily report: 24 hours, coded by hand, and at the end of the month the days added up.

I was the operations engineer in the office, and rig performance was my job. It had started offshore. In February 2015 we put one drilling connection on a page: five steps, each one timed, 351 seconds in all. Later that year, on four rigs, we built software that recovered the drilling system's own data and turned it into 98 indicators for the operations on the drill floor.

In 2016 we took it to the whole fleet, built in house, with no third party in the process. The data left the rig's drilling system through a serial adapter with one pin cut. Each rig gave one reading a second, 86,400 a day. We cut that stream into operations (a connection, a trip, a casing run) and it came to about 500 rows a day. Each operation had a target, and the time over the target was added up as invisible lost time.

Then we could draw the day.

Twenty-one percent of a rig's time was drilling. That is about five hours in twenty-four with the bit making hole. Static flat time was 46%: making up the bottom-hole assembly, cementing, cutting drill line, moving the rig. Dynamic flat time was 32%: tripping pipe, running casing and riser. Downtime, the number a day-rate contract penalises, was 1%.

Flat time is the industry's name for time spent not making hole that still counts as productive, because the work is on the critical path. A well cannot be drilled without it. It was close to four fifths of the clock, it counted as productive, and until then we had no instrument for it.

On 23 October SLB reported its third quarter. In his prepared remarks, its chief executive counted more than 750 thousand feet of automated drilling in the quarter, up nearly 50% in a year.

That number is true, and it is good.

Feet measure the fifth of the clock when the bit is turning.

The other four fifths show up further down the same companies' case studies. In SLB's example from Angola, automation cut the time before a connection by 47% and the time after it by 25%. In NOV's example from the Middle East, the wells reached total depth on one bit run where the offset wells needed three or four. A run that is not made is a trip that is not made.

Today we work with drilling contractors, and we see it again. Drilling is one part of the equation. A lot of flat time is related to planning and to waiting on operations: materials that have to be delivered, a spare part that has to arrive. None of that is in the drilling data. It is in the supply chain, in the operational reports and in the plans. So we put all of it on one map, and several agents work over that map at once, each on its own part of the operation, with people deciding what gets done. The work then reaches the planning, the materials and the spares, not only the fifth of the time when the bit is turning.

My split is one offshore fleet, in 2016 and 2017, and the proportions move from rig to rig. The order of the questions does not: first what the day is made of, then what the machine speeds up.

The same goes for anything sold on the step it makes faster, a model included. The step has a name and a number. The buyer needs to know what share of the day that step is.

Diego Mercadal started as a commissioning engineer on high-voltage motors and generators, joined an offshore drilling contractor as a rig hand, worked several positions in the drilling crew, and ended up running its AI/ML function. He is now co-founder and CEO of Wonder DataLabs.